2. History

The Voivodeship Inspectorate of Environmental Protection in Poznań made the first efforts to obtain subsidy funding under the PL04 Operational Programme “Saving energy and promotion of renewable energy sources" under the European Economic Area Financial Mechanism 2009-2014 in 2014.
On 11 September 2014, an application was filed for co-financing of the project entitled “Improvement of the energy efficiency of buildings of the Voivodeship Inspectorate of Environmental Protection in Poznań and its Regional Office in Kalisz."

  • January 2015 - positive substantive and technical assessment of the application;
  • March 2015 - project on the reserve list;
  • July 2015 - extension of the ranking list;
  • 30 July 2015 - signing of the agreement No. 248/2015/Wn15/OA-xn-04/D;
  • from September 2015 - technical design documentation, permissions, expert opinions, etc.
  • October 2015 - information on the possible extension of the project;
  • November 2015 - application for extension of the scope of the project to cover buildings of the Regional Offices in Konin and Piła;
  • February 2016 - Annex No. 1/31 prolonging the deadline for eligibility of expenditure to 30 April 2017;
  • June 2016 - Annex No. 2/268 for extension of the subsidy to cover the proposed scope.
  • June 2016 - commencement of construction work in Kalisz.
  • October 2016 - commencement of construction works in Poznań.
  • October 2016 - completion of construction works in Kalisz.
  • February 2017 - resignation from extended project.
  • March 2017 - completion of construction works in Poznan.
  • April 2017 - completion of the project.
 

Implementation of the project under the name: „Improving energy efficiency of buildings of the Regional Inspectorate of Environmental Protection (WIOŚ) in Poznan and its branch office in Kalisz co-financed by the EEA Financial Mechanism 2009-2014
2009-2014